Services/Products  arrow   PAC Planer  arrow   Concrete
PAC PLANNER - C O N C R E T E Print E-mail


Add/Edit Concrete Cost.
(1)_Right Click on an area element. Select "Add Cost" or "Edit Cost" from the "Concrete" submenu. (2)_Add/Edit Concrete window is shown. Parameters are entered. (3)_Next to the "Remove" from "Concrete" submenu the cost value is updated.
Overview Concrete Cost.
(1)_Right Click on an area element. Select "Overview Concrete Cost" from the "Concrete" submenu. (2)_Table with the detailed concrete cost is shown. (3)_Pressing the "Export to XSL" button exports the details in a file readable in Excel.
Concrete Report.
(1)_Select "Concrete" from the Report menu. (2)_Table with all detailed concrete cost is shown. (3)_Pressing the "Export to XSL" button exports the details in a file readable in Excel.